|
The following day more transport
aircraft brought naval assault troops, a light anti-aircraft unit, and a company
from Infantry Regiment 396. By 2 July radio communications had been set up with
the mainland, and the construction of anti-aircraft batteries was begun in
Guernsey and Jersey on 4 July. All the existing forts that were initially
thought to be a threat were found to be deserted and disused, and the Germans
quickly set about putting these to use. The remainder of the early defences were
nothing more than earthworks and lightweight structures. Early in 1941 Hitler
turned his attention to fortifying the Channel Islands. He feared that once
Operation ‘Barbarossa’ (the invasion of Russia, beginning on 22 June) was
underway, the British may well attempt to re-capture the Channel Islands. Around
this time the Germans began to employ local labour for the construction of its
fortifications. |
|  | |
| |

|
In
March 1941 the order went out to strengthen the defences on the Islands and more troops, together with several Navy and
Army construction battalions, began to
arrive. Reinforced field order fortifications started to appear around the
coast. This work was not yet being
undertaken by the O.T., but by the Army and Navy construction units. These were
mainly units of company strength taken from Construction Battalions, Bridge
Construction Battalions, Fortress Construction Battalions, and Railway
Construction Battalions (despite the fact that no railways were being
constructed). These units arrived in March 1941 and stayed for 3-6 months, after
which the O.T. began to arrive. A report dated April 1941 stated that on
Guernsey one 22cm battery (Strassburg) was in the process of construction, and
would be combat ready by the beginning of May. Work
on the early reinforced field order defences continued while the various Festpistab
units carried out their surveys.
These fortifications were designed to
be incorporated into the later defences. A report dated June 1941 stated that
the 22cm battery was now combat ready in permanent positions with most ancillary
shelters complete while construction of the gun platforms for a 15cm battery was
in progress. |
|
In July 1941 Army Coastal Batteries
462 and 463 - each with four 15cm K18 guns, 464, 465, and 466 - each with three
21cm Mrs 18 howitzers, and 471 and 472 - each with four 22cm K532(f) guns were
transferred to Guernsey. By the end of the month Batteries 462-466 were combat
ready, with the remaining crews being left to wait for their guns to be
reconditioned in Germany; five anti-aircraft batteries were also combat ready.
In September 1941 Higher Command requested the installation of one battery of 4
x 38cm guns and four batteries of 4 x 15cm SK C/28 guns. By early 1941 Hitler
had ordered that the defences of the Channel Islands were to be further
strengthened and asked for a full survey to ascertain what was needed to make
the islands impregnable. The survey began on July 1941, when Festpistab 19 (Fortress Engineer Staff 19) with Abschnittgruppe I/19 and II/19 (Sector Groups) arrived in Guernsey. Overseeing
this operation was Generalmajor Rudolf Schmetzer, Inspekteur der Landbefestigung bei Oberbefehlshaber West (Inspector of Ground Fortifications at Supreme
Commander-in-the-West) Early in October 1941 Generalmajor Schmetzer submitted his survey and, two days
later following a high level conference in Berlin, Hitler signed
his Directive and approved plans to turn the Channel Islands into “Impregnable
Fortresses”. It was only after this meeting that the short-term programme (to
be completed in 14 months) got underway. |
|

| |
|

|
The various strong points around the
coastline were first constructed by the troops and later by military
construction units. The existing forts were already sited in good strategic
positions and these were adapted by the addition of extra defences. Strong
points consisted mainly of casemated coastal guns, personnel shelters,
searchlight bunkers and anti-tank guns enfilading the beaches. Approval was
given for the installation of a 30.5cm battery (Mirus) in place of a proposed
38cm battery and the replacement
of the 22cm guns of Batterie Strassburg with 15cm SK C/28 guns. Whilst the 30.5cm battery
was constructed, the replacement of the Strassburg guns would never materialise. As early as July 1941 it was apparent
that the Fortress Engineers alone would not be able to cope with the scale of
the works, and the O.T. should be called in to assist. By November 1941, Dr
Fritz Todt had visited the three islands where he issued Construction Orders
identifying the following areas of responsibility: 1.
Individual troops - field fortifications (trenches,
foxholes etc.) 2. Divisional Engineers -
distribution of land mines and flame throwers. 3. Army Construction Battalions -
reinforced field order defences 4. Fortress Engineers/Construction Battalions -
supplying and installing fortress weapons, some tunnelling, transport of heavy
loads, compiling construction progress reports and maps, ordering and
supervising O.T. tasks. 5. Organisation Todt - quarrying, construction of roads,
power stations, most tunnelling, supervising civilian building firms, sea
transport, controlling non-military labour and building fortress standard
defences. |
|
By early November 1941
considerable amounts of stores and personnel had begun to arrive, and the
fortification programme was soon to be underway. On
15 December 1941 Hitler issued the order for the construction of the Atlantic
Wall. To oversee this, Generalmajor
Schmetzer left the Channel Islands and was replaced by Festungspionierkommadeur
XIV under Oberst von Marnitz. Elizabeth College was chosen as
headquarters, shared with Festpistab 19 which had been there since the previous July. Subordinate units included -
Abschnitt Gr.I/19, Abschnitt Gr.II/19, Festungsbaubtl.19, as well as
Rock-Drilling, Mining and Compressor Companies. Despite the large amount of
works initially planned for the island, not everything was achieved. Three of
the four 15cm SK batteries that were requested never arrived; only Batterie
Steinbruch was constructed. Of
the seven proposed naval range-finding towers (Marinepeilstande), only four would be built. Likewise, of the six
8.8cm Flak batteries, only two were built to near fortress
standard with the other four remaining in field emplacements. Of the many
tunnels started on the island, most were left unfinished due to lack of labour
and materials. Construction work in the Channel Islands peaked in April 1943.
Italy’s withdrawal from the war in September 1943 resulted in thousands of
workers being transferred from the Islands to build more fortifications on the
Franco-Italian border. Nevertheless, a huge amount was achieved
during 1941 to 1943. Set back from the coast on the higher ground were three Naval Batteries, nine
Army Coastal batteries (HKAR/1265) and five Army Divisional batteries (Artillery
Regiment 379) with guns ranging from 10cm to 30.5cm. Observation posts were
constructed inland and on the cliffs. The entire coastline was ringed with
resistance nests and strong points, and 54,000 mines had been laid by the
beginning of April 1944.In addition substantial headquarters bunkers were built
for the various arms of services. This was linked by a fortress telephone
network running diagonally across the island from north to southwest. The cable
was buried 2 metres
deep, and passed through four Netzknotenpunkt (Network junction bunkers), 21 Kabelschaltstellen (Cable switching posts), and a repeater station. By
the end of January 1944 the fortifications on the Channel Islands had consumed
484,000 (Festung Guernsey Table lists 613,000cubic metre by 1/9/44) cubic metres
of concrete compared with 6,100,000 cubic metres for the rest of the Atlantic
Wall. In addition, the amount of excavation work is even more interesting. At
the start of 1944 the construction of the Atlantic Wall had necessitated the
removal of 255,000 cubic metres, while at the same time 244,000 cubic metres had
been excavated in the Channel Islands. Taking into account these statistics
alone, the Atlantic Wall could perhaps have been made much stronger had the
effort and resources used on the Islands been utilised elsewhere After
liberation, the massive clear-up operation began. British troops and German
prisoners of war set about clearing the thousands of mines laid around the
coast. Weapons of all calibres had to be assembled in various locations prior to
being
taken out to sea for dumping. The 30.5cm guns of Batterie Mirus were cut up for scrap some years after the war. Gradually most of the coastal
fortifications were backfilled and landscaped over. Many field order
gun-emplacements were situated on agricultural land, and these were gradually
eradicated and the land returned to farming. However, only a small proportion of
the structures have been demolished, mostly to make way for re-development. One
bunker was removed from the New Jetty in St Peter Port due to fears that weight
may collapse the jetty. Several observation posts serving the inland gun batteries were removed. The
German Power Station in the Bouet was demolished to make way for a housing
estate. The biggest losses were Naval Range-finding Tower MP 1 at Chouet, which
collapsed into the quarry
in 1991, and Batterie
Steinbruch, which apart from two surviving flak bunkers
was also destroyed by quarrying. Now some sixty years on feelings have changed, and a
growing interest in the occupation of the Islands has meant that there are
groups dedicated to restoring the various sites. The Occupation Museum is
responsible for the restoration of a 10.5cm Jäger casemate at Fort Hommet and
the Naval Range-finding Tower MP 3 at Pleinmont; both are open regularly throughout
the season. Guernsey Armouries have restored one of the 22cm emplacements of Batterie
Dollmann together with trenches and ancillary bunkers. An
original 22cm barrel and replica carriage has been reinstalled. The Occupation
Society has also restored the Naval Signals Bunker at St Jacques.
|